Two plans for one cave: the life-of-mine strategy and the schedule that runs it every day.

Block caving and underground mining companies depend on two separate but connected plans: a strategic mine plan covering the whole life of mine, and a detailed tactical plan that turns its decisions into the schedule governing day-to-day operations. Because it is long term, the strategic plan is exposed to internal and external forces: new findings about the orebody, technical advances, changes in the economy or the market. Tactical plans, including the mine schedule, are the calculated short-term response that keeps the mine on its long-term goals. GEOVIA reduces the risk in the first and unlocks the potential of the second, and ACALA brings both to Indonesian underground mines.

A grid of 96 draw points on an extraction level, opened progressively as the undercut advances month by month, shaded by how much of each column has been drawn extraction level, plan view · undercut advances left to right12 × 8 draw points month 18 · 48 of 96 draw points opened · 21% of the cave column drawn Illustrative. Dark: opened and drawing. Light: not yet undercut. Shade deepens as the column is drawn.
A block cave is a schedule before it is a mine: the undercut sequence, the rate each draw point opens and the tonnes drawn per point decide grade, dilution and whether the cave propagates. Strategic and tactical plans have to agree on it. Drag the handle from month 0 to 36.
Block cavingUndercutting a massive orebody so the ore collapses into voids and is drawn from below.
Undercut sequenceThe order and rate at which the cave is initiated across the footprint.
Draw pointWhere broken ore is loaded; the unit the schedule controls.
GeomechanicsRock behaviour simulated to choose method, sequence and support.
Extraction sequenceWhich blocks are mined when, to meet ratio and quality targets.
Central repositoryTopography, scheduling parameters and all pertinent data in one place, updated by everyone.
ACALA's Principal Mining Engineer discussing with underground mining engineers at the face
ACALA’s Principal Mining Engineer in discussion with the mine’s underground engineers at the face.

The idea

Future-proof both plans: reduce the risk in the strategy and unlock the tactical potential.

To future-proof strategic and tactical plans, block cavers and underground miners must consider every operational scenario and lock in the plans that deliver the full potential, and therefore the maximum value, of the operation.

Histogram of net present value from five hundred simulated schedules, with P10, P50 and P90 marked and the single fixed-value answer shown at its percentile500 schedules run with noise on the fixed valuesnet present value of the same cave, simulatedP10$321 MP50$379 MP90$444 Mone fixed-value answer · P74NPV, $ millionNoise on the fixed values turns one number into a range you can plan against
Reduce the risk in your strategic mine planning.

Reduce the risk in strategic planning

GEOVIA strategic planning tools simulate geomechanical rock behaviour and determine the optimal mining method, extraction sequence, plant configuration, stockpile and dumping requirements. Risk assessment is built into every step by adding uncontrolled variables, such as noise around traditionally fixed values, so the mine can absorb unforeseen forces.

Blended gold grade held inside a target band across twelve periods, above a stacked bar showing how much came from each source in each periodTwelve periods held inside a 5.0–6.0 g/t Au bandthe blend decides which source is drawn when6.005.00g/t Au123456789101112high-grade stopelow-grade stopestockpileperiodChange a condition and the schedule is rebuilt, not renegotiated
Unlock the full potential of your tactical mine plans.

Unlock the tactical potential

A central repository where planners collect, collate and update all pertinent data, then advanced blending algorithms choose which blocks are mined when to meet material ratio and quality targets, with virtually unlimited iterations of short- and long-term schedules as conditions change.

Key benefits

What GEOVIA changes for a caving or underground operation.

Fewer surprises

Scenarios that consider price, demand and operating costs, with uncertainty inside the plan, reduce the risk that the strategy is overtaken by events.

Optimised production

Mine-to-mill planning integrated, so bottlenecks are found in the plan and performance improves at the draw point and the plant.

Deeper, safer mining

Geological modelling and geomechanical simulation let miners assess ore at depth, choose method and sequence, and run the operation with fewer geological surprises.

The workflow

From geology model to daily draw order.

The GEOVIA cave planning roles cover the whole chain, from tunnel and draw point layout to the day’s draw order, and hand over to each other without re-entering data.

1Model

Geology, geotechnics and the cave footprint

A detailed geological model for accurate resource assessment, with rock behaviour simulated to choose method and footprint.

Tools

  • GEOVIA Surpac; Geology Model and Resource Model solutions; geomechanical simulation on the platform.

Result

  • A footprint and a method with the risk stated.
2Strategy

Long-term cave plan

Tunnels, draw points and rings set up rapidly; flow modelling and multiple scenarios; superior run-time on full-sized projects.

Tools

  • GEOVIA Cave Long-term Planner (GSK); Strategic Mine Planning solution.

Result

  • A life-of-mine cave schedule with the undercut sequence.
3Mid-term

NPV-optimised production schedule

Schedules that optimise NPV under tonnage, grade and equipment constraints, with realistic undercut sequences in PCBC and exact undercut ring shapes.

Tools

  • GEOVIA Cave Mid-term Planner (GTP); Tactical Mine Planning solution.

Result

  • Draw bells sequenced with the undercut; a residual block model after analysis.
4Daily

Draw orders under changing conditions

Schedules kept current, daily draw orders by multiple methods, grade managed from draw point samples, and interfaces to LHD dispatch and monitoring.

Tools

  • GEOVIA Cave Operations Scheduler (GPN); Mine Operational Management solution.

Result

  • The cave drawn as planned, and the plan updated from what was drawn.

Questions people ask

Block Caving and Underground Mining FAQ

What is meant by underground mining?
Extracting minerals or ores from beneath the surface through tunnels, shafts or declines, typically for deposits at depth or once shallow deposits are exhausted. Methods include drift, slope and shaft mining, and the operation needs specialised equipment, ventilation and safety systems.
What are the four types of mining?
Surface mining, which removes overlying material; underground mining, which accesses deep deposits; placer mining, which extracts minerals from alluvial deposits; and in-situ mining, which dissolves minerals underground. The choice depends on deposit depth and mineral type.
Is underground mining bad for the environment?
Conducted responsibly with proper safeguards it has advantages over some other methods, but its impact can still be significant: water pollution, subsidence and accidents can occur. Responsible practice, regulatory compliance and ongoing monitoring are essential.
What happens in an underground mine?
Shafts or tunnels give access to the ore, which is blasted, crushed and transported to the surface for processing. In a block cave the ore is undercut and drawn from draw points below as it collapses.
How does ACALA help?
Licences for Surpac, MineSched and the GEOVIA cave planning roles, underground design and planning services, and training for planners on their own data.

Next step

Send us the footprint and the block model. We will show you the undercut sequence and what it does to grade.

A working session with an ACALA planner on your own data, then a proposal for licences, planning services or training.