The schedule that carries a cave strategy into the working week.

A strategic plan decides where the cave goes. The tactical plan decides what happens next month: which development advances, which draw points open, how much comes out of each, and what grade the plant should expect. GEOVIA Tactical Mine Planning for Caving builds development and production schedules on one horizon, so a plan can be checked against what the mine actually did and adjusted without starting again. ACALA supplies the licences in Indonesia and prepares the schedules when a client would rather hand the work over.

The solution in one view

  • InputAn assessment of the potential project, based on new data.
  • Six stepsObjectives, tactical plan, cave flow, scenarios, financials, reporting.
  • OutputA development and production schedule the mine can run, and a basis to check what it actually did against.
  • Who runs itYour own planners on a GEOVIA licence, or the ACALA team on your data.
Tactical planThe short-horizon schedule that turns strategy into work orders.
Development scheduleThe advance that has to happen before ore can be drawn.
Production scheduleTonnes and grade drawn per period, by draw point.
Cave flow simulationHow broken ore moves through the cave, and what grade arrives.
Sublevel cavingA caving method scheduled on the same platform as block caving.
Reaction timeHow quickly a plan can be redone once the mine reports what happened.

Where this starts

Three situations that bring a caving operation to tactical planning.

The plan and the mine have drifted apart

Production came in different from the schedule, and there is no quick way to fold what actually happened back into the next plan.

Development and production planned separately

Two schedules that have to agree are built in two places, so the advance needed to open a draw point is found late.

Scenarios take too long to be useful

By the time an alternative schedule is ready, the question it was meant to answer has already been decided.

The workflow

Six steps, from objectives to a schedule the mine can run.

Development and production are scheduled together on one horizon, so the plan can guide execution and be reassessed against what the mine reports.

1Frame

Define objectives, KPIs and constraints

What the schedule has to deliver, and the limits it works inside.

Decided here

  • Production targets, grade requirements, development and equipment limits.

Result

  • A basis the schedule and every alternative are measured against.
2Schedule

Generate the tactical mine plan

Development advance and production extraction on one schedule, built from caving rules and constraints.

Decided here

  • Draw point opening sequence, draw rates, development required to support them.

Result

  • A practical plan with predicted production and grade by period.
3Flow

Perform cave flow simulation

How the broken ore moves, and what actually reports to each draw point.

Decided here

  • Expected grade at the draw point, mixing and dilution through the period.

Result

  • A grade forecast the plant can plan against.
4Scenarios

Scenario analysis and optimisation

Complex modelling of alternatives across block caving and sublevel caving, compared on the same basis.

Decided here

  • Which schedule to run, and what it costs to choose a different one.

Result

  • A preferred schedule with its alternatives documented.
5Money

Prepare financial models

The schedule expressed as cost and revenue over the planning horizon.

Decided here

  • Operating profile, cost per tonne, value of the chosen sequence.

Result

  • Numbers that tie back to the schedule that produced them.
6Share

Reports, dashboards and a shared view

The plan validated in 3D animation, published to everyone who has to act on it.

Decided here

  • What is committed, on which version of the data, visible to operations and management.

Result

  • A feasibility study report, a life-of-mine plan, and a go or no-go decision.

The workflow at a glance

The same six steps, end to end.

Tactical caving workflow: an input assessment, six numbered steps from objectives to reporting, an output of development and production schedules, and a feedback loop from reporting back to the tactical planInput, six steps, output — one horizon for development and productionINPUTAn assessment of thepotential project,based on new data.1Objectivesdefine2Tacticalplangenerate3Cave flowsimulate4Scenarioscompare5Financialsvalue6ReportingshareOUTPUTA development andproduction schedulethe mine can run,and a basis to checkit against.what the mine actually did folds back into the next scheduleDevelopment and production are scheduled together, so the plan can be reassessed, not rebuilt.
The workflow as it runs on the platform, drawn from the steps described above.

What it changes

What the solution is meant to give a caving operation.

History that informs the next plan

Trends and updates are determined from what the mine has already reported, rather than assumed again each cycle.

Complex scenarios modelled

Block caving and sublevel caving alternatives modelled in detail and compared on the same basis.

Plans that include grade

Schedules carry production extraction and predicted grade, so the plant is planning against the same numbers.

Plans that can be validated

The schedule is visualised in 3D animation, with caving geomechanical simulation brought into the planning process.

Faster reaction

Rework and reaction time fall, so a revised schedule is ready while the decision it supports is still open.

One version to work from

Visual data and dashboards give operations and management the same picture of what is committed.

Questions people ask

Tactical Mine Planning for Caving FAQ

How is this different from strategic planning for caving?
Strategic planning decides the method, the footprint and the sequence across the life of the mine. Tactical planning schedules the development and production that deliver it over the coming period. The strategic side is covered on its own page.
Does it schedule development as well as production?
Yes. Development and production are combined on one horizon, which is what makes it possible to see whether the advance needed to open a draw point will be there in time.
Does it cover sublevel caving?
Yes. Scenario modelling covers block caving and sublevel caving, which is where the two methods can be compared against the same targets.
Can ACALA prepare the schedule instead of our team?
Yes. ACALA works either way: licences and support for your own planners, or the schedule prepared by ACALA engineers on your data.
How do we get pricing?
Send the scope through the contact form or on WhatsApp. A quote for licences, scheduling work or training follows within a few working days.

Next step

Tell us what the cave schedule has to deliver next, and where it is slipping.

A quote for licences, scheduling work or training within a few working days.