MineSched tip – update Haul Roads that have been adjusted in Surpac (GMP)
Following the creation of Haul routes and running the schedule to get the results in MineSched, if you want to modify haul road strings in Surpac (GMP), you can use MineSched to update it quickly and easily using the following steps.

By @Shoaib ZIA
Following the creation of Haul routes and running the schedule to get the results in MineSched, if you want to modify haul road strings in Surpac (GMP), you can use MineSched to update it quickly and easily using the following steps.

1. Update your haul road design in Surpac as normal (using edit, move tools etc).

2. Open the original MineSched Haul Road Scenario.
3. On “Roads” tab it will give you a warning that “The geometry source for the road has been modified”.
4. Select this road and then click on Refresh Roads button to update the road. Note if there are multiple roads with warnings, you can select and refresh all the roads in this one step.
5. A warning panel will pop up, if you want to refresh the roads or not. Click continue

6. It will also tell you in the “Refresh Roads summary” tab which roads have been refreshed.

7. The Warning sign should now have disappeared from the “Roads” tab.
8. The Haul Roads are now updated and ready in MineSched
When to use this
Haul roads change often during a mine life: ramps are redesigned, new dump access is added and pit stages move. In a schedule, haul distances drive truck cycle times and fleet requirements, so outdated road geometry quietly produces wrong haulage hours. Refreshing the roads keeps the schedule tied to the current design without rebuilding the road network from scratch.
This is most useful in short and medium term planning, where design updates are frequent and the schedule must be rerun quickly to see the effect on equipment needs.
Practical checks
- Keep a copy of the original road strings and of the scenario before editing, so you can go back if the change is not accepted.
- After editing, check that road strings are still connected at junctions and that end points sit where the network expects them.
- Review gradients and elevations along edited segments to confirm they are drivable for the planned trucks.
- Compare haulage results before and after the refresh and confirm the change in distance matches the size of the design change.
Related at ACALA
Explore GEOVIA MineSched and GEOVIA Surpac. For faster ramp and road design inside Surpac, see Rapid Design, a design menu built from Surpac TCL macros.
Next step
Want your team to work this way every day?
Our courses teach these workflows in GEOVIA Surpac, Whittle and MineSched, and our support team answers the questions that come up afterwards.