Surpac tip – Checking linear clearance around existing and planned drillholes

For roles such as an Underground Geologist, Underground Planning Engineer or an Underground Surveyor, it is necessary to be able to view planned underground workings with existing drill holes and to view planned drill holes with existing workings.
This capability helps ensure the safety of both underground miners and workers on the surface who are operating within the area of influence from the dangers associated around drillholes in the areas of influence.
Typical dangers could include:
- Inrush of water down the drill holes into the underground workings
- Drilling into active drives where boggers and jumbos are working
- Air blast up the drill holes during underground firings, or
- Air blast down the drill holes during open pit firings
To view workings subject to exiting and planned drillholes:
1. Open up the drillhole database and display the drillholes.
2. Open up the design solids.

3. Select Solids>meshing tools>linear clearance analysis


4. The maximum clearance, will be the radius around the drill holes that will be checked. A report file of the holes within this radius will be produced.


This information can then be used with planes for plotting plans for the underground crew.
When to use this
Many underground operations include clearance checks in their permit-to-drill and permit-to-fire processes. Running the analysis before drilling a new hole from surface, or before firing near known holes, gives documented evidence that the hazard was considered and that the right people were told.
The report becomes most useful when it is combined with information on the condition of each hole, because a grouted hole and an open hole carry very different risks. Plans produced from the report, showing holes near active headings, are easier for crews to use than a list of hole names and distances, especially at shift change.
Practical checks
- Set the clearance radius from the site’s standoff rules rather than a default value.
- Include as-built workings as well as planned ones, using the latest survey.
- Record the status of each hole in the report, for example grouted, open or blocked, where it is known.
- Repeat the check whenever designs or drilling plans change, and file each report with its date.
Related at ACALA
Read more about GEOVIA Surpac for underground work. ACALA runs GEOVIA training for geologists and engineers, and you can find more Surpac tips here.