Surpac Tip – Designing ramps with varying slope angle and berm width
In pit design, engineers often need to adjust slope angles and berm widths based on rock stability. GEOVIA Surpac supports this by using values stored in the D-field of the pit design string file, with slope angles taken from D1 and berm widths from D2, enabling precise and flexible pit design.
Originally shared on the GEOVIA user community by Suvradip DATTA. Adapted and republished by ACALA for Indonesian users.

In pit design, engineers often need to adjust slope angles and berm widths based on rock stability. GEOVIA Surpac supports this by using values stored in the D-field of the pit design string file, with slope angles taken from D1 and berm widths from D2, enabling precise and flexible pit design.
In the example below, the images show the pit bottom boundary with varying slope angle (in decimal degrees) & berm width stored in D1 & D2 field respectively:
To start the pit design, first go to Design›Pit design›Select slope method and select “descriptions” as Design slope angle method:
To define ramp properties, go to Design›Pit design›New ramp; then select the ramp starting points:
Next to expand the bench, go toDesign›Expand segment›By bench height, and select the pit bottom segment; then go to Design›Pit design›Display slope angle:
It will generate the ramp as well with specified ramp properties.
Now to expand the pit further with berm width, go to Design›Expand segment›By berm width and select Berm width method as “descriptions”; then go to Design›Pit design›Display berm width:

The same D-field value will be copied further and maintain the varying slope angle and berm width as more benches are expanded.To check the varying slope angle through the surface color banding; open the designed pit DTM file into graphics and go to Display›Surface or solid with color banding as shown below:
When to use this
Rock conditions around a pit are rarely uniform. Weathered zones, fault corridors and walls facing different directions often need their own slope angles and berm widths. A single setting for the whole pit is either unsafe in weak ground or too conservative in competent rock, which adds waste stripping.
Storing the values on each point of the design string lets the pit follow the geotechnical domain map directly. It also keeps the design traceable: anyone reviewing it can query a segment and see which slope and berm were applied there, which helps during design approval.
Practical checks
- Confirm the slope values are in decimal degrees and the berm widths use the same length unit as the coordinates.
- Before expanding, check that every point on the starting string carries values in both fields.
- Review transitions between segments in plan view, as abrupt changes can create irregular crests that need smoothing.
- Keep a copy of the original string, and measure a few finished benches against the intended angle and berm width.
Related at ACALA
For quicker pit and ramp work in GEOVIA Surpac, see Rapid Design, built from Surpac TCL macros. ACALA also offers an open pit mine design and planning service.