Surpac tip – How to see the difference between planned and mined solids

Discover how to generate reconciliation heat maps to see the compliance of the as-built surfaces against plan with GEOVIA Surpac deviation analysis tool.
When to use this
Comparing as-built surveys with planned surfaces shows how well the design was followed. Overbreak in walls adds dilution and may undercut berms, while underbreak leaves ore behind and can create toe problems. A colour map of the deviation makes these areas easy to find and discuss with drill and blast and survey teams.
Used each month, these maps build a record of design compliance, help explain differences between planned and actual tonnes, and show where blast designs or wall control practices should change. Reviewing deviation soon after each survey, while crews still remember the blasts, makes it easier to link problem areas to specific causes.
Practical checks
- Record the survey pickup date and the design version used in each comparison.
- Confirm both surfaces share the same coordinate system and elevation datum.
- Set the colour ranges to match the site’s tolerance for overbreak and underbreak.
- Check survey coverage; gaps in the pickup can look like deviation when they are only missing data.
Related at ACALA
See GEOVIA Surpac for reconciliation tools. ACALA supports design compliance work through its open pit mine design and planning service and planning and optimization service.
Next step
Want your team to work this way every day?