Surpac Tip – Pit Design, top to bottom
Mining/Design Engineers often need to design pits from a top boundary with varying RL values, while subsequent benches require fixed RL designs with ramps. GEOVIA Surpac provides the capability to create benches with fixed RL, using delta Z up to the desired elevation, making pit design more efficient and precise.

By @Suvradip DATTA
Mining/Design Engineers often need to design pits from a top boundary with varying RL values, while subsequent benches require fixed RL designs with ramps. GEOVIA Surpac provides the capability to create benches with fixed RL, using delta Z up to the desired elevation, making pit design more efficient and precise.

To start designing the pit, first go to Design›Pit Design›New Ramp; then select the ramp starting points and define the ramp properties as shown below:


Next to define Design Slope Angle Method, go to Design›Pit Design›Select Slope Method and choose design slope. Then go to Design›Pit Design›Set Slope Gradient for entering bench slope gradient manually as shown below:


To design the next bench at 1030 mRL, go to Design›Expand Segment›To elevation; and select the pit top string file, it will create bench line at 1030 mRL where RL values are more than 1030.


Now to expand the pit further with berm with, go to Design›Expand Segment›By berm width and select Berm creation method as “delta z down to elevation >=” and set Limiting elevation as “1030”:
It will generate a ramp as well with the specified ramp properties:
To move further with 10 mt bench height and 5 mt berm width up to 900 mRL, it will create the pit as per the images below:
When to use this
Designing from the top down suits pits whose limit is set at the surface, for example by a lease boundary, infrastructure, a watercourse or an existing crest on uneven ground. Because the top string follows the topography, the first step brings the design to a regular bench elevation; from there, fixed bench heights continue downward.
Matching bench elevations to the site’s standard levels keeps the design consistent with drill and blast benches, survey control and reporting. It also makes it easier to compare the design against other stages or earlier versions.
Practical checks
- Check that the top boundary string sits on the current topography surface, not on an older survey.
- Confirm the target bench elevations follow the site’s bench convention before expanding.
- Measure the ramp in a few places to confirm its gradient and width match the input properties.
- Intersect the finished design with topography to confirm it daylights correctly, and check the pit floor still meets the minimum mining width.
Related at ACALA
To speed up pit and ramp design in GEOVIA Surpac, see Rapid Design, a menu built from Surpac TCL macros. Our open pit mine design and planning service can also take on full pit and ramp design work.
Next step
Want your team to work this way every day?
Our courses teach these workflows in GEOVIA Surpac, Whittle and MineSched, and our support team answers the questions that come up afterwards.